By the end you'll be able to
- Create a task that repeats (every week, every month).
- Know who gets which due-date notification.
- Export and import the plan with MS Project without duplicating anything.
What the system doesn't do
- It doesn't create every occurrence at once: the next one appears when you complete the current one.
- An MS Project plan that didn't come from here comes in as new tasks.
Exercise 6 · What repeats and what goes out (6 min)
- Create "Weekly progress report" repeating every Monday, with Lucia or yourself as the assignee.
- Complete it and check that the one for the following Monday appeared.
- Export the plan to MS Project (XML).
You got it right if…
after completing the report there's a new one dated the following Monday, and you have the XML file downloaded.
Learn more
- User manual §11 (Tasks) and the "Recurring tasks" help article.