Lesson 1 of 7 · 2:50 min

Task, subtask and deadline

The three pieces of the plan: the task with a start and an end, the subtask that hangs from it, and the single-date deadline.

For: Everyone

By the end you'll be able to

  1. Create a task with dates, a priority and an assignee.
  2. Create subtasks to break up the work.
  3. Create a single-date deadline (a milestone or a delivery).

What the system doesn't do

  1. A task with no assignee only notifies the project lead.
  2. The parent task adjusts its dates to cover its subtasks, but the plan doesn't reschedule itself when something slips.
  3. What deadlines are called (deliverable, due date, milestone) depends on your organization.

Exercise 1 · The first pieces (8 min)

In your practice project:

  1. Create the task "Phase 1 — Warehouse survey" running from next Monday to three weeks later, High priority, with you as the assignee.
  2. Create three subtasks: Waco visit, Temple visit and Houston visit, one week each.
  3. Create the deadline "Final report delivered" on 12/15.

You got it right if…

the tree shows the phase with its three visits hanging from it, and the deadline appears with its date.

Learn more

  1. User manual §11.1 (Tasks view) and §11.2 (Creating a task).
  2. Review video: onb-05-plan-de-trabajo.