IU-104 · Learner workbook

# IU-104 · Student workbook

Iurefficient School. Do these in the classroom (demo.iurefficient.com) or in your own instance, in your practice project from IU-101.

Lesson 1 · Task, subtask and deadline

Exercise 1 · The first pieces (8 min)

In your practice project:

  1. Create the task "Phase 1 — Warehouse survey" running from next Monday to three weeks later, High priority, with you as the assignee.
  2. Create three subtasks: Waco visit, Temple visit and Houston visit, one week each.
  3. Create the deadline "Final report delivered" on 12/15.

You got it right if… the tree shows the phase with its three visits hanging from it, and the deadline appears with its date.

Lesson 2 · Assignees: people, external contacts and roles

Exercise 2 · Who does what (5 min)

  1. Assign the Temple visit to a teammate (in the classroom, whoever your instructor tells you).
  2. Assign the Houston visit to Lucia Ramirez (external contact).
  3. On the Waco visit, leave the assignee blank and request whatever role your instance has (for example, "Consultant").

You got it right if… the list shows a teammate, an external contact and a role waiting to be filled.

Lesson 3 · The views: Tree, Kanban and Gantt

Exercise 3 · Three questions, three views (5 min)

  1. In the Tree, expand Phase 1 and count its subtasks.
  2. In Kanban, move the Waco visit to "In Process."
  3. In the Gantt chart, use "Fit" and find the diamond for the final delivery.

You got it right if… the Waco visit also shows "In Process" in the Tree (it's the same information).

Lesson 4 · The Sheet and bulk editing (no fear)

Exercise 4 · Fix it all at once (5 min)

  1. In the Sheet, enter estimated hours for the three visits (24 each) and set Phase 1 to High priority.
  2. Save.
  3. Change the priority of the three visits to "Low" by mistake, save, and use "Undo."

You got it right if… after undoing, the visits get their priority back and keep their 24 hours.

Lesson 5 · Dependencies and the Gantt chart

Exercise 5 · The analysis chain (6 min)

  1. Create the tasks "Receive Houston shrink data" and "Shrink analysis" (Phase 2).
  2. Make the analysis depend on receiving the shrink data.
  3. Export the Gantt chart as an image.

You got it right if… the Gantt chart shows an arrow from "Receive Houston shrink data" to "Shrink analysis," and you have the image downloaded.

Lesson 6 · Recurring tasks, notifications and MS Project

Exercise 6 · What repeats and what goes out (6 min)

  1. Create "Weekly progress report" repeating every Monday, with Lucia or yourself as the assignee.
  2. Complete it and check that the one for the following Monday appeared.
  3. Export the plan to MS Project (XML).

You got it right if… after completing the report there's a new one dated the following Monday, and you have the XML file downloaded.

Lesson 7 · Capstone practice

The mission

  1. Phases. Three tasks: Survey, Analysis and Proposal, with dates that follow one another.
  2. Subtasks. The three visits in Phase 1; "Receive Houston shrink data," "Inventory turnover analysis" and "Shrink analysis" in Phase 2; "Draft the improvement proposal" in Phase 3.
  3. Deadlines. "Leadership presentation" and "Final report delivered" (12/15).
  4. Assignees. At least one person, one external contact and one role.
  5. Dependencies. "Shrink analysis" depends on "Receive Houston shrink data."
  6. Recurring. "Weekly progress report" every Monday.